ARCELORMITTAL Gand :

 


Détails :

  • Coupling, pickling 2 tandems
  • Industrial Transfer of MIEBACH Welding Machine

Services provided:

  • Dismantled Miebach welding machine on pickling line inlet 2 / Reinforcement 50T – 1.5 j -
  • Dismantled and transferred Miebach Laser Welding machine , accumulator outlet Tandem line 2 to pickling line inlet 2
  • Dismantled electrical panels
  • Dismantled hydraulic consoles and interconnection piping
  • Dismantled punchers, shears, inlet and outlet centralizer
  • Handled and transported C frame 46; Base frame 55T. Total weight: 160T.
  • Re-assembled base frame , laser adjusted rails of C frame and peripheral machines
  • Designed, Fabricated and fitted new interconnection piping
  • Electric rewiring.

Resources:

  • Workforce : 25 people - 2 shifts-
  • Deadline : 13 days from August to September 2007



 