On existing mill 400T. 20 housings 15 days , day/night shifts
Assembly of mechanical equipment - approximate total
weight : 625 Tons including :
4 universal stands
5 vertical stands
8 horizontal stands
3 shears
Design ,supply, assembly, rinsing
of hydraulic piping, of motor and housing cooling systems , compressed air, lubrication. Length of piping
installed ; 3000
meters
Fabrication of outlet
mechanical equipment according to customer drawings and transfer of
cooling bed to the leveler. Fabrication and installation – approximate weight 100 Tons
Resources
Total labour: 20000 hours
40 people working 2 shifts
10 weeks including 8 in mechanical
operations- 01/08-15/10/2007