Access to site
Eriem
 

UGINE & ALZ Genk :

 


Details :

  • Industrial Transfer of a rolling mill from LDD Dudelange (Luxemburg) to Ugine ALZ Genk (Belgium).

Services provided:

  • Labeling and dismantling of mechanical equipment ,piping, power electronics
  • Total weight : 2000 Tons including :
    • Cylinders : 600 tons
    • Housings : 200 tons
    • Grinding machine and concrete block : 160 tons
    • Equipment and emulsions : 1140 tons
  • Transport
    • 15 wide load trucks
    • 105 trucks
  • Re-assembling :
    • Designed interconnection piping lay out
    • Pre-fabricated, assembled hydraulic piping (3500 meters), for emulsions, cooling systems, compressed air, lubrication (10 000 inches).
    • Used mechanical equipment.
    • Integrated new SMS manufacturing equipment ,mill inlet and outlet carriage coilers and uncoilers
    • Rewired power and wired signal cable.

Particularity :

  • Dismantled et transported concrete block for grinding machine (160 tons) gaining 6 months of reinstallation – Civil Engineering-

Planning :

  • Total duration: 6 months including 4 months for dismantling and 2 months for loading and transport.

Means implemented:

  • Overall planning: September 2007 to February 2008
  • Mechanical work: 15 people
  • Piping : 20 people
  • Electricity : 15 people



 

Visuals

 